Click here to make tpub.com your Home Page

Page Title: Team Member Preparation for both Previsit and ORR
Back | Up | Next

Click here for thousands of PDF manuals

Google


Web
www.tpub.com

Home

   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Logistics
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
   
   

 



DOE-HDBK-3012-96
RC
Make security clearance arrangements for the ORR previsit. Complete DOE F
5631.20 (277's), Request for Visit or Access Approval forms for previsit team.
Discuss access requirements with the site point-of-contact before the previsit to
determine which Sigmas are needed. Discuss security procedures for any uncleared
team members.
Make sure the team has maps of the site and how to get to the site and hotel from
the airport. Maps should be requested from the site.
Make contact with site coordinator to introduce and discuss logistical questions.
Discuss sigma/security requirements for cleared and uncleared team members and if
there are any special procedures to bring in equipment, such as laptop computers, or
supplies such as computer disks.
Verify that all team members' clearance information and all necessary forms for
access to the site have been forwarded to the site. Verify that this has occurred at
least one week prior to the previsit.
Complete the necessary forms for access to the site for all team members and
forward the data to the site.
Verify that all reference material needed by the team from HQ has been provided
to team members four to five days before the team's arrival for the previsit and
ORR.
Team Member Preparation for both Previsit and ORR
TM  
Each team member should receive and review their data packet. The data packet
provides team members with information on the site, their assignments, including
deliverables, and responsibilities of the team member.
Each team member is to contact the Hotel to confirm their reservation and
guarantee it with a credit card.
Each contractor is responsible for providing clearance information to the RC.
Provide the following clearance information:
1. team members' name
2. social security number
3. date of birth
4. organization/company name
5. the type of clearance held.
4