Click here to make tpub.com your Home Page

Page Title: Approval Authority Expectations and Scope for the Review cont'd
Back | Up | Next

Click here for thousands of PDF manuals

Google


Web
www.tpub.com

Home

   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Logistics
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
   
   

 



DOE-HDBK-3027-99
g. The Approval Authority should specify the deliverables of the review. The letter may
specify a report documenting the process and the results, or only a summary of the results.
Either should require a recommendation for future action.
h. The prerequisite conditions that the Approval Authority considers necessary before the
verification may commence. The prerequisites should be specific and measurable to
minimize any confusion as to what is expected. Effective prerequisites which have been
used in past verifications include:
For Phase I Verifications
C The ISMS Description has been formally submitted
C Corporate/Site manuals of practice supporting the ISMS Description are
available for review
C Authorization Agreements (draft/approved) are available for review
C ISMS Verification Team Leader has been appointed, team has been designated
and trained, and ISMS Verification Review Plan has been approved and
promulgated
For Phase II Verifications
C The ISMS as described in the approved ISMS Description has been
implemented
C ISMS Verification Team Leader has been appointed, team has been designated
and trained, and ISMS Verification Review Plan has been approved and
promulgated
i. There should be a discussion of previous reviews that could affect the scope of the
verification. Examples of reviews that may affect the scope of a review include a previous
ORR, a SAR review and associated SER, or the implementation of Work Smart
Standards or Enhanced Work Planning programs. The Approval Authority should define
the amount of consideration to be given to each of these previous reviews or assessments.
j. The estimated date or commitment for the verification with recognition that the review
will not be started until the prerequisites have been achieved.
k. Any additional information useful to the designated Team Leader for meeting the
expectations of the Approval Authority.
A-4-4


Privacy Statement - Press Release - Copyright Information. - Contact Us

Integrated Publishing, Inc. - A (SDVOSB) Service Disabled Veteran Owned Small Business