A shift work coordination meeting should be held shortly before the start of each shift.
This meeting should be attended by oncoming shift supervision for each of the groups
supporting the maintenance schedule, including maintenance, health physics, technical
staff engineering, area coordinators, and task coordinators, for jobs requiring significant
support. The Operations Supervisor for the oncoming shift should also attend. The
shift work coordination meeting should address all scheduled work for the upcoming
shift by exception and should modify the schedule as necessary to reflect last-minute
changes.  Reissue of the daily schedule to reflect these changes should not be -
necessary. Items requiring multi-discipline support should be identified to the respective
support groups and an estimate of the quantity of resources and the time required should
be provided. Each attendee should leave the meeting with a clear under-standing of
what their work group should do on the upcoming shift. The meeting should end in
time for supervisors to return to their work groups before the shift starts.
Assignments for problem resolution should be made at meetings, but resolution should
not be attempted during the meeting. The meetings should not be used as the primary
method to determine status of maintenance activities.
3.6.5 Performance Monitoring
Performance measures should be developed to monitor the progress toward meeting
plant maintenance goals (see DOE "Guidelines to Good Practices f or M anagem ent
Inv olv em ent at DOE N uclear Facilities") Progress toward meeting these goals should
be monitored frequently. Results of the routine monitoring should be reported to plant
management. Examples of goals that are typically monitored include:
rate of activity completion
percent compliance to the daily schedule
progress against the schedule
amount and rate of bulk work (nonscheduled or listed work) completed
expended man-hours versus planned man-hours by each craft or work group
number of industrial accidents
expended man-rem versus planned man-rem
amount of radwaste generated
32