DOE-STD-3006-95
both the Contractor and DOE ORR findings. The action plan should be discussed in the closeout
meeting and should contain the following elements:
a. The finding, as written in the report submitted by the ORR team, and whether the finding is a
prestart or post-start finding.
b. A detailed proposed action plan for addressing the deficiencies identified in that finding. The
proposed action plan should provide evaluation of any overall programmatic deficiencies or root
causes related to a specific finding which may lead to further similar occurrences and include actions
addressing such deficiencies or root causes. For prestart findings in the DOE ORR, DOE must
approve the contractor's proposed corrective action plan.
c. The proposed dates by which the action elements will be completed. If the corrective actions for a
finding are phased, then the dates for each phase should be detailed.
d. If it is a post-start finding, a description of the risks and mitigating actions, if any, to be taken
during the interim which will reduce the risks associated with the finding to an acceptable level before
final correction. Include justification that the activity can proceed with acceptable risk. DOE line
management shall verify that the corrective action plan has been entered into the appropriate quality
program issue management system.
5.7.3 Action Tracking/Closure Methodology. Monitoring and verification of satisfactory closure
of prestart findings from both the Contractor and DOE ORRs is a management responsibility. The
ORR team leader and team members may be required to assist in the verification or adequate resolution
of prestart findings. DOE 0 425.1 defines elements of the required process to close ORR prestart
findings. This is accomplished by development of a closure package that is reviewed and certified by
the facility management and further reviewed by DOE management for findings from the DOE ORR.
These procedures should be documented either in a facility wide requirement or within the individual
ORR Implementation Plan. Closure packages should contain the following information:
a. The finding, written verbatim from the original report, and identifying the finding as a prestart or
post-start finding.
45