5.1.9 ORR Final Report. An ORR Final Report shall be prepared. The Report should contain a
brief summary of the review activities, the conclusions reached, the basis for those conclusions, and
the findings identified. The ORR Final Report may also identify observations that would not impact
startup, restart or shutdown but, if corrected, could lead to excellence in operations. The ORR Final
Report shall make a conclusion as to whether startup or restart of the facility can proceed safely. In
addition, there shall be a statement in the ORR Final Report as to whether all identified non-
compliances or schedules for gaining compliance with applicable DOE Orders, directives, and
Standards/Requirements Identification Documents have been identified in writing; have been formally
approved; and, in the opinion of the Operational Readiness Review team maintain adequate protection
of the public health and safety, worker safety, or the environment.
The ORR Final Report should include a section describing the lessons learned during the ORR,
including a discussion of both the process and the technical issues identified. Section 5.8 of this
standard further discusses lessons learned.
The ORR Final Report should include a section that provides the ORR team members the opportunity
to discuss differing professional opinions, non-judgmental general comments, and observations. The
ORR Final Report is described in more detail in Section 5.9.3.
5.1.10 Contractor Declaration of Readiness to Proceed. Once the contractor ORR process has
been completed, the contractor should develop an action plan which provides the methodology and the
schedule for resolution of the findings from the ORR. Prior to forwarding the Readiness to Proceed
Memorandum to DOE, the prestart findings shall be resolved and the action plan, including schedule
of completion for the remaining findings, should be prepared. DOE will not begin the DOE ORR
until the contractor's Readiness to Proceed Memorandum has been received and accepted. Once the
DOE ORR process has been completed and all DOE findings and comments are satisfactorily
resolved, formal approval to start the facility will be granted in accordance with the requirements
approved in the ORR plan-of-action. The Readiness to Proceed Memorandum is described in more
detail in Section 5.9.4.
5.2 Roles and responsibilities for the DOE Field Activities including Area Offices and Operations
Offices. The following items are a compilation of the responsibilities of the Operations and Area