DOE-STD-3006-2000
formally approved; and, in the opinion of the Operational Readiness Review team maintain adequate
protection of the public health and safety, worker safety, or the environment.
The ORR Final Report should include a section describing the lessons learned during the ORR, including
a discussion of both the process and the technical issues identified. Section 5.8 of this standard further
discusses lessons learned.
The ORR Final Report should include a section that provides the ORR team members the opportunity to
discuss differing professional opinions, non-judgmental general comments, and observations. The ORR
Final Report is described in more detail in Section 5.9.3.
5.1.12 Contractor Declaration of Readiness to Proceed. Once the contractor ORR process has been
completed, the contractor should develop an action plan which provides the methodology and the
schedule for resolution of the findings from the ORR. Prior to forwarding the Readiness to Proceed
Memorandum to DOE, the prestart findings shall be resolved and the action plan, including schedule of
completion for the remaining findings, should be prepared. DOE will not begin the DOE ORR until the
contractor's Readiness to Proceed Memorandum has been received and accepted. Once the DOE ORR
process has been completed and all DOE findings and comments are satisfactorily resolved, formal
approval to start the facility is granted in accordance with the requirements approved in the ORR plan-of-
action. The Readiness to Proceed Memorandum is described in more detail in Section 5.9.4.
5.2 Roles and responsibilities for the DOE Field Activities including Area Offices and Operations
Offices. The following items are a compilation of the responsibilities of the Operations and Area Offices
in the execution of the new start and the restart readiness review process. Each action or responsibility is
described in more detail elsewhere in this standard or in DOE O 425.1B. The purpose of this section is
to collect the applicable requirements in one place. The unique circumstances of the individual situation
determine the specific applicability of any individual requirement.
5.2.1 DOE Prepares Implementing Procedures. Prepare implementing procedures as necessary to
carry out the requirements of the readiness review process (both ORR and RA) in accordance with the
requirements of DOE O 425.1B and the guidance of this standard. In those cases where the Operations
Office manager intends to delegate the decision authority for specific actions or individual
29