5.9.1.2.8 Official to Approve Start of the ORR. In most circumstances for the DOE ORR, this is the
authorization authority designated in the approved startup notification plans. Designation of the
authorization authority is made in accordance with the requirements of DOE O 425.1B. For the
contractor ORR, the official designated to approve the start of the ORR should be a line manager senior
to the manager responsible for achieving overall readiness to start operations.
5.9.1.2.9 Official to Approve Startup or Restart of the Facility. This is the individual specified in
DOE O 425.1B based on a new start or restart circumstances. The specific authorization authority is
listed in the startup notification plan.
5.9.1.2.10 Reviewers' Approval. List the individuals by name and title who prepared and reviewed
this document. The signature indicates that they have reviewed the document and recommend approval
by the authorization authority listed.
5.9.1.2.11 Distribution. This is a listing of the individuals and organizations who receive copies of
the ORR plan-of-action following approval. Individuals and organizations are listed who have either
responsibilities or interests in the new start or restart process.
5.9.2 ORR Implementation Plans. The ORR Implementation Plan is developed by the team
responsible for conducting the ORR. The Implementation Plan is approved by the Team Leader
designated in the ORR plan-of-action. This ORR Implementation Plan documents not only the process
the team uses to conduct the review, but also defines the rationale for that process. The documentation
includes the selection of criteria and review approaches and the procedures the team uses to develop
findings and conclusions, and the criteria to be applied to categorize findings as prestart and post-start.
The ORR Implementation Plan is the document that provides for the depth of evaluation of the ORR
breadth and execution of other details in the approved ORR plan-of-action.
The ORR Implementation Plan should provide sufficient detail to serve as both information to
management and guidance to the ORR team members. The team preparing the ORR Implementation
Plan requires a thorough understanding of the facility and its associated issues. Pre-development on-site
facility visits and interviews may be required before the ORR Implementation Plan can be adequately
developed.
50