6.0 ESTABLISHING A SYSTEM FOR RESOLVING ACTION ITEMS
AND IMPLEMENTING CORRECTIVE ACTIONS
Activities documenting and tracking implementation of corrective actions or safety
improvements are not part of a PrHA report. However, the PSM Rule requires a documented,
integrated system for managing and monitoring action items. This system must assure that
action items and recommendations are addressed and documented in a timely manner.
Implementation schedules for corrective actions or safety improvements must be tracked.
Finally, the system must assure that all affected operating and maintenance personnel and other
affected employees are notified of planned actions.
In addition to these requirements, if a PrHA is conducted to satisfy safety analysis requirements
of 10 CFR 830 Subpart B NUCLEAR SAFETY MANAGEMENT, SAFETY BASIS
REQUIREMENTS, the resolution of action items must be documented to obtain approval of the
safety analysis and the startup of the facility. In this case, the contractor may be required to
satisfy specific safety criteria before an action item is considered resolved.
6.1
Process Hazard Analysis Action Items and Recommendations
The critical result of a PrHA is the list of action items developed by the PrHA team. Action
items are written any time the team thinks that additional effort is warranted to review further a
specific scenario, to eliminate a hazard, or to reduce risks. Usually, action items do not
recommend specific corrective actions. They are meant to alert management to potential
problems. Sometimes, action items may suggest alternatives to be considered. However, if a
problem is simple, if a PrHA team is quite experienced, or if there is only one obvious solution,
an action item may be written to recommend a specific corrective action.
The action items from a PrHA are presented to management for review and evaluation, and for
determination of what, if any, corrective actions should be taken to eliminate hazards or to
reduce risks through preventative, protective, or mitigative measures. Because many action
items may be generated during a PrHA, the team may choose to rank the action items according
to the probability of occurrence of their corresponding accident scenarios or the severity of their
consequences or both. If the PrHA team is quite experienced, it may also choose to rank the
action items based on the anticipated time and resources required to implement changes.
6.2
Criteria for Corrective Actions and Safety Improvements
Management can use a variety of criteria to select and prioritize corrective actions and safety
improvements. They include costs, other competing priorities, implementation schedules, the
effectiveness of risk reduction, and technical feasibility. These criteria, as well as management
decisions about corrective actions, must be documented. If after evaluating an action item,
management chooses to take no further action, that decision must also be documented. In
addition to requiring documentation of management decisions, the PSM Rule requires a system
to track implementation of corrective actions to be made.