2.2.4 Findings and Recommendations
DOE contractors should establish a system to:
promptly address the team's findings and recommendations;
assure that recommendations are resolved in a timely manner and that resolutions
are documented;
document actions to be taken;
develop a written completion schedule for the action steps;
complete actions as soon as possible;
communicate the actions to all affected personnel.
DOE contractors must retain PrHAs and updates for each process covered by the PSM Rule,
along with documented resolutions of recommendations, for the life of the process.
2.2.5 Acceptable Methodology
The PSM Rule specifies that DOE contractors use one or more of the following methodologies,
as appropriate, to determine and evaluate the hazards of the process being analyzed:
What-If
Checklist
What-If/Checklist
Hazard and Operability Study
Failure Mode and Effects Analysis
Fault Tree Analysis
An appropriate equivalent methodology.