TASK C: SELECT A PrHA METHOD FOR EACH PROCESS.
Paragraph (e)(2) of the PSM Rule
implies that it is the responsibility of the DOE contractor to select the review method, not the
choice of the team conducting the review. In some cases, a combination of methods may be
used.
TASK D: ESTIMATE THE MANPOWER REQUIRED AND DEVELOP A STAFFING PLAN.
The
manpower required to conduct a PrHA depends on many factors, including the review method
selected, the training and experience of the review team, the extent and complexity of the
process, its instrumentation and controls, and whether the process is a procedure-oriented
operation (such as a batch reaction) or a continuous operation (such as petroleum refining). In
addition, reviews and updates of existing PrHAs tend to be less time consuming than initial
analyses. Guidance for estimating PrHA time requirements is given for each review method in
Sections 4.1 to 4.6.
Based on the analysis methods selected in Task C, the status of existing PrHAs, and the time
requirements for the methods reviewed in Sections 4.1 to 4.6, the manpower requirements for
PrHAs, and reviews and updates, can be estimated. Comparing these requirements with
available personnel indicates where additional staffing may be needed, either on a temporary or
longer-term basis.
TASK E: SELECT A PROCESS TO BE ANALYZED.
This selection should be straightforward: the
process to be analyzed should be the process highest on the prioritized list (Task B). If there are
exceptions, justifications should be carefully documented. For example, if the highest process
on a prioritized list has some significant process changes planned, it may be reasonable to
analyze the process being modified along with its proposed changes.
TASK F: ASSEMBLE THE PrHA TEAM AND TRAIN THE TEAM MEMBERS.
Regardless of the method
selected, the PSM Rule requires all PrHAs to be performed by a team. This team is an ad hoc
committee, formed solely to conduct a PrHA for an assigned process. It is disbanded after the analysis,
including documentation, has been completed.
The review team must have expertise in engineering and process operations, and at least one
team member must have experience and knowledge specific to the process being evaluated. If
the process is a new design, the experience requirement may be satisfied by bringing in a person
from a sister plant or from a similar or precursor process. In addition, at least one member of
the team must be knowledgeable in the hazard analysis methodology being used (see note at the
end of Section 1.0).
All team members should be familiar with PrHA objectives, the PrHA method to be used, and
their roles in performing the PrHA. A 1- or 2-hour overview at the beginning of the first team
8