| DOE-HDBK-1100-2004
review session is generally sufficient for this purpose. However, the more demanding PrHA
methods, such as fault tree analysis (FTA), require more training and/or a greater depth of
experience than less-rigorous methods, such as what-if and checklist analyses.
TASK G: SCHEDULE THE PrHAs.
To assure full participation by all team members, the team
leader should set up a meeting schedule that is realistic but as condensed as possible to provide a
concentrated, focused analysis.
A typical schedule is 1 to 3 days per week, with the team meeting 4 to 6 hours per day, until the
analysis is completed. The involvement of remote site personnel and/or consultants may
necessitate an even more ambitious schedule. However, the efficiency of the team tends to
decline if there are more than three, 6-hour meetings per week.
The team leader must devote additional time outside of team meetings for meeting preparation
and documentation. Preparation, such as assembling pertinent documents and deciding how
each review is approached, may take 8 to 12 hours per P&ID. Documentation typically takes
another 8 hours per P&ID.
TASK H: CONDUCT THE PrHA.
PrHAs are conducted after all up-to-date process safety
information is assembled and the team members are appropriately trained. The team should
walkdown the process and facility immediately prior to the analysis, to have the process fresh in
mind and to get a sense of the scale and orientation of the process, the surrounding facilities, and
the location of operating and co-located personnel.
A description of PrHA methods is given in Section 4 of this document. Keys to successful
PrHAs are full preparation, punctuality, focused discussions, careful evaluation of each scenario
for risk to onsite and offsite persons, and documentation of the analysis as soon as possible after
each team meeting.
TASK I: REPORT THE ANALYSIS RESULTS.
The PrHA report documents the scope, approach,
identified hazards, analyzed scenarios, and action items resulting from the PrHAs. The report
should receive close scrutiny, both for compliance with the PSM Rule and for explanations of
each action item. Guidance for reporting the PrHA results are given in Section 5.1.
TASK J: APPROVE THE REPORT AND ACTION ITEMS.
The PrHA team should present its findings
to operating management when the draft report is complete. Operating management may wish
to ask questions about the analysis or have a debriefing meeting on ways to improve the PSM
program. The team should then finalize the report. The approval of the final PrHA report by
operating management is a commitment by management to implement all action items.
Section 5.2 addresses the PrHA review process.
TASK K: ADDRESS THE ACTION ITEMS.
All action items must be addressed by operating
management, and their resolutions must be documented. Corrective actions and safety
improvements approved by management must be fully implemented in a timely manner.
Timeliness can be assured by assigning responsibilities and completion dates to all action items