554 Contamination Monitoring
1.
In addition to the requirements of Article 551, contamination monitoring programs should be established to ensure
that surveys are performed at a frequency that is consistent with the existing and potential hazards and activities
planned in the area. The following survey frequencies are suggested and should be modified as necessary to ensure
area hazards are adequately characterized, based upon facility-specific experience:
a.
Prior to transfer of equipment and material from one radiological buffer area established for contamination
control to another, unless the material was monitored immediately prior to this transfer, such as upon removal
from a contamination area
b.
Prior to transfer of equipment and material from high contamination areas within radiological buffer areas
unless precautions such as bagging or wrapping are taken prior to transfer
c.
Daily, at contamination area control points, change areas, or step-off pads when in use, or per shift in high use
situations
d.
Daily, in office space located in radiological buffer areas
e.
Daily, in lunch rooms or eating areas near radiological buffer areas
f.
Daily in accessible areas where operations are under way that are likely to produce hot particles
g.
Weekly, in routinely occupied radiological buffer areas
h.
Weekly, or upon entry if entries are less frequent, in contamination areas and other areas where materials
having removable contamination exceeding the Table 2-2 values are handled or stored
i.
Weekly, or upon entry if entries are less frequent, where contamination area boundaries or postings are
located
j.
During initial entry into a known or suspected contamination area, periodically during work, at completion of
job, or as specified in a radiological work permit
k.
Monthly , in and around areas of fixed contamination
l.
After a leak or spill of radioactive materials.
2.
Articles 421 and 422 provide requirements and guidance for material release surveys.
3.
When radioactive material is received (other than gaseous or special form materials), contamination monitoring of
the received packages shall performed if:
a.
The package is labeled in accordance with the applicable transportation requirements (e.g., Radioactive White
I or Yellow II or III label) [see 835.405(b)(1)]; or
b.
The package has been transported as low specific activity material on an exclusive vehicle [see
835.405(b)(2)].
The external surfaces of all packages received from transportation should be monitored to determine the external
contamination level, unless the packaged materials are not capable of creating a contamination hazard (i.e., the
packages contain only gaseous or special form materials). These surveys are used to ensure compliance with
Department of Transportation regulations and applicable DOE Orders and to identify appropriate postings and
access control measures. These measures should be established as soon as practicable after receipt.
4.
Monitoring shall also be performed when a received package of radioactive material shows evidence of
degradation, such as packages that are crushed, wet, or damaged [see 835.405(b)(3)], unless the packages contain
only special form or gaseous radioactive material.
5.
Monitoring of received packages of radioactive material shall be performed as soon as practicable following
receipt, but not later than eight hours following the beginning of the working day following the receipt of the
package [see 835.405(d)].