| DOE-STD-1120-2005/Vol. 2
READINESS CHECKLIST
PROJECT:
PROJECT MGR:
ACTION
ACCEPTABLE?
ASSIGNEE
Yes
No
a.
Heavy equipment operator
b.
Welder
c.
Health physics technician (including radiological controls)
d.
Special D&D equipment operator
e.
Radioactive waste operations
f.
Waste process equipment operator
g.
Plutonium handling
4.
Site-specific hazards indoctrination
5.
Emergency response drills conducted and documented
6.
Medical examination (including fitness requirements)
7.
Respirator and breathing air testing and qualification
8.
Special PPE training and qualification
9.
"Dry-run" or demonstration successfully conducted and
documented for any new technology or equipment to be utilized
10. Mockup training is completed and documented
11. Work package indoctrination with the workers and walkdowns
are completed
12. Other training as needed (e.g., fire watch, gas-free inspector, and
rigger)
XIV.
Subcontractors: Ensure that All Subcontractors are
Mobilized as Required and All Pre-Job and
Mobilization Requirements are Completed
1.
Pre-job deliverables are received and accepted by the project
a.
Health and safety programs and plans
b.
QA plan/program
c.
Worker certifications (e.g., training, medical, special
equipment, operator, and resume)
d.
Equipment certifications
e.
Special operating procedures
2.
Subcontractor resources
a.
All required subcontract personnel are onsite and have
successfully completed site-specific qualification
requirements
F-11
|