|
| DOE-EM-STD-5503-94
2.0. KEY PERSONNEL
2.1. BACKGROUND
This chapter provides guidance to assist in the preparation of the Key Personnel portion of the
site-specific HASP. In this section, the HASP should:
Identify an individual who has the authority to direct all activities;
Identify the other personnel needed for the project and assign their general functions and
responsibilities;
Show lines of authority, responsibility, and means of contact; and
Identify the interface with the response community.
2.2. ORGANIZATIONAL STRUCTURE
The HASP should specifically identify the names and organizational relationships among the
DOE, contractor, and subcontractor key personnel, such as the Project Manager, Field Team
Leader, and Site Safety and Health Officer (SSHO). Designated alternates for the key personnel,
responsibilities, lines of authority, methods of communication, and an organizational structure
should be identified. If specific key job responsibilities listed in this chapter are not needed, or
more than one function is to be performed by a person, those responsibilities should be addressed
in the HASP.
During the first stages of planning, an organizational structure that supports the overall objectives
of the project should be developed. An explanation of the structure including the chain of
command and overall responsibilities of supervisors and employees in carrying out the health and
safety program should be included in the HASP. An organizational chart should be developed
depicting the structure and identifying all key personnel and other onsite and offsite personnel (see
Figure 2-1). The chart should be placed in a central location, and included in the HASP. At a
minimum, the organizational chart should include the Project Manager, the SSHO, the Field Team
Leader, the Command Post Supervisor, the Decontamination Station Officer(s), site security, and
the specialty team. In addition, it is recommended that a list of DOE and contractor personnel
and a list of offsite organizations (see Figure 2-2) to be contacted in the event of an emergency be
included with the organizational chart.
As the project progresses, it may be necessary to modify some organizational aspects, such as
personnel responsibilities and authorities, so that individual tasks can be performed as efficiently
and safely as possible. Any changes to the overall organizational structure should be recorded in
the appropriate sections of the HASP that are developed for individual phases or tasks. These
specific changes should be communicated to all parties involved.
2-1
|
Privacy Statement - Press Release - Copyright Information. - Contact Us |