| DOE-HDBK-3012-96
ORR DEFICIENCY FORM 2 SAMPLE
Functional
Objective
Finding X
Pre-Start X
Issue No.: EP.2-1
Area: EP
No.: 2
Observe.
Post-Start
Date: 8/24/94
ISSUE: XXX Area Compliance Schedules Approvals (XXX-DOE-5500.3A-CAS-93-005,
006,024) committed to complete a facility Interim Hazards Assessment leading to a compliant
Emergency Action Level (EAL) procedure has not been completed on schedule (August 22,
1994).
REQUIREMENT: EALs are require by DOE Order 5500.3A, 11.be)[2] and
5500.3A,11.c(3)[2] ". . ., the specific criteria used to recognize and categorize events, must be
developed for the spectrum of potential Operational Emergencies identified by the hazards
assessment."
REFERENCE(S): XXX-DOE-5500.3A-CAS-93-005; XXX-DOE-5500.3A-CAS-93-006;
XXX-DOE-5500.3A-CAS-93-024; XXX-940093 memorandum, X-Area USQ Resolution
Matrix.
DISCUSSION: Compliance Schedule Approval (CSA) agreements were approved for required
upgrades to the Emergency Preparedness Program. Due to a variety of circumstances, the EAL
procedure was not developed in conformance with the agreed to schedule. The CSA
compensatory actions remain in place while a new CSA is evaluated. Reportedly, XXXX
(CONTRACTOR) has proposed a new schedule for compliance with an end date of 10/31/94.
CONCLUSION: This order compliance issue should be evaluated and a new schedule accepted
by DOE. Pending resolution of this matter, the agreed upon compensatory measures should
continue. Resolution of this matter prior to restart is considered appropriate due to the
significance of the topic and the need for Headquarters agreement on the delay in achieving
compliance.