| DOE-HDBK-1092-2004
7.4.15
REMOVING INSULATING GOODS FROM CONDUCTORS..........................................7-8
7.4.16
CLEANING AND INSPECTING .......................................................................................7-8
7.5
PROTECTIVE GROUNDING OF LINES AND EQUIPMENT ....................................................7-8
7.5.1
PURPOSE........................................................................................................................7-8
7.5.1.1
REDUCE THE POTENTIAL VOLTAGE DIFFERENCES ACROSS THE WORKER..7-9
7.5.2
APPLICATION .................................................................................................................7-9
7.5.2.1
DEENERGIZED LINES ...............................................................................................7-9
7.5.2.2
NEW CONSTRUCTION OR DISMANTLING OF FACILITIES..................................7-10
7.5.2.3
MINIMUM APPROACH DISTANCE FROM UNGROUNDED CONDUCTORS ........7-10
7.5.2.4
VISIBLE THREE-PHASE SHORT AND GROUND REQUIRED ...............................7-10
7.5.2.5
GROUND CIRCUIT ...................................................................................................7-10
7.5.3
GROUNDING EQUIPMENT ..........................................................................................7-11
7.5.3.1
AVAILABILITY ...........................................................................................................7-11
7.5.3.2
APPROVED CAPACITY............................................................................................7-11
7.5.3.3
GROUNDING CABLES AND HARDWARE ..............................................................7-11
7.5.3.4
GROUNDING CABLES .............................................................................................7-11
7.5.3.4.1
STRANDING .........................................................................................................7-11
7.5.3.4.2
JACKETS ..............................................................................................................7-11
7.5.3.4.3
FERRULES ...........................................................................................................7-12
7.5.3.4.4
HANDLING OF GROUNDING CABLE .................................................................7-12
7.5.3.4.5
SIZE OF GROUNDING CABLE ............................................................................7-12
7.5.3.4.6
GROUNDING CABLE LENGTH............................................................................7-12
7.5.3.4.7
GROUNDING CLAMPS ........................................................................................7-12
7.5.3.4.7.1
CLAMP TYPES...............................................................................................7-12
7.5.3.4.7.2
CLAMP JAWS.................................................................................................7-13
7.5.3.4.8
GROUNDING CLUSTER BARS ...........................................................................7-13
7.5.3.4.9
TEMPORARY GROUND RODS ...........................................................................7-13
7.5.4
TESTING BEFORE INSTALLING GROUNDS ..............................................................7-14
7.5.5
ATTACHING AND REMOVING GROUNDS .................................................................7-14
7.5.6.1
WORK LOCATION ....................................................................................................7-14
7.5.6.3
OTHER LOCATIONS ................................................................................................7-15
7.5.7
TESTING WITHOUT GROUNDS ..................................................................................7-15
7.5.8
GROUND PERSONNEL................................................................................................7-15
7.6
INSTALLING OR REMOVING CONDUCTORS ......................................................................7-15
7.6.1
WORKING ON ENERGIZED LINE OR EQUIPMENT ...................................................7-15
7.6.2
STRINGING OR REMOVING DEENERGIZED CONDUCTORS..................................7-16
7.6.3
STRINGING ADJACENT TO ENERGIZED LINES .......................................................7-17