|
| DOE-HDBK-1092-2004
18. GFCIs shall be used for 120-V ac power unless such power is supplied by a portable or
vehicle-mounted two-wire, single-phase generator rated not more than 5 kW, where the
circuit conductors of the generator are insulated from the generator frame and all other
grounded surfaces. (See Section 6.4).
19. All cables and insulated wires that do not have grounded conducting sheaths or shielding
should be treated as bare conductors. They shall be considered energized unless approved
methods have been used to determine that they are deenergized. Barricade or cover these
conductors with protective equipment or devices that will be within reach of a worker's
position.
20. Where multiple cables are present the cable to be worked on shall be identified by electrical
means unless its identity is obvious. [See 29 CFR 1910.269(t)(5)]. Where cable has one or
more abnormalities that could be an indication of an impending fault, the defective cable
shall be deenergized, except when service load conditions and a lack of feasible alternatives
require that the cable remain energized. In that case, employees may enter the manhole if
they are protected by the affects of the failure by flash blankets or other devices capable of
containing the adverse effects of the fault. [See 29 CFR 1910.269(t)(7)].
7.10.2 WORKING ON ENERGIZED UNDERGROUND CABLES
In general, work should not be performed on energized underground cables. However, strictly
external work, not requiring an appreciable change in location of the cable, may be performed
under direct supervision. Energized cables that are to be moved shall be inspected for defects.
[See 29 CFR 1910.269(t)(6)].
7.10.3 TERMINALS OF UNDERGROUND CABLES (POTHEADS)
Before work is started, the overhead line connections to a cable terminal upon which work is to
be performed should be either:
1. Deenergized and grounded or
2. Disconnected and covered with protective equipment.
7.11 FERRO-RESONANCE
Ferro-resonance can generate overvoltages of up to 12 times line-to-ground source voltage
upon opening of a single-phase device or a poorly synchronized three-phase device. Violent
failure can occur, exposing personnel to the high-voltage failure and accompanying conditions.
Ferro-resonant conditions can result in damage to lightning arresters, switching devices, buried
cable, transformers, and associated equipment.
Ferro-resonance can be initiated when all of the following elements are present and the
switching means at dip point or takeoff is either a single-phase device or an unsynchronized
three-phase device that does not operate all phases within one-half cycle:
i.
System grounded at the source but with no ground at the transformer bank, such as a
transformer or transformer bank connected delta on a grounded-wye system.
ii. Shielded cable or overhead conductor length sufficient to create the capacitance necessary.
7-23
|
Privacy Statement - Press Release - Copyright Information. - Contact Us |