DOE-HDBK-1101-96
is addressed in DOE O 430.1, LIFE CYCLE ASSET MANAGEMENT. DOE-STD-1073-93, Guide
for Operational Configuration Management Program, applies to existing facilities. DOE O 420.1,
FACILITY SAFETY, requires that modifications conform to requirements for new facilities. For
years, DOE accident investigation classes have taught the use of a technique called Change Analysis
to identify changes that contribute to accidents. This emphasizes the importance of a good MOC
system in accident prevention, because virtually all accidents involve some degree of change.
The MOC process should facilitate identification of potential unreviewed safety questions
introduced by process changes. DOE DOE O 424.1 describes how such issues should be resolved.
Documentation Requirements
There is no specific documentation requirement for MOC beyond developing a written MOC
procedure and updating the existing process safety information and operating and maintenance
procedures [Q83]. As a practical matter, MOC procedures should include the development of a
request for change form. A sample form is provided in Exhibit 2.10 at the end of this section.
Minimum Implementation Criteria
For a management of change program to be effective, DOE contractor personnel at all levels must be
trained to recognize and understand the ramifications of proposed changes on the safe operation of a
chemical process, including the interdependencies and interrelationships among facility functions,
processes, and activities. For example, a simple change in a valve design may potentially require
changes and modifications to the normal and emergency operating procedures, maintenance
routines, and staff training. Such issues must be resolved before the change is implemented.
An effective MOC program should contain a means to initiate (request), track, review, and approve
changes. Written MOC procedures must address responsibilities, the basis for a change, and the
impacts of the change, including the following isssues.
Assignment of responsibility for requesting changes to existing systems, processes, and
procedures.
Assignment of responsibility for approving changes.
The criteria for approving changes.
Assignment of responsibility for implementing changes.
The basis for the change should be documented on the request for change form, including a
discussion of the technical, safety, and operational needs for the change, and an analysis of the
proposed change, including:
acceptable safety/risk assessment methods and approaches;
impact on potential for release;
format and content of the analysis.
Impacts of the proposed change include:
procedures, functions, processes, and activities, such as maintenance and operation
80