| Not Needed
Comments
Title
In Appendix G of LANL
Orders and Rules of
in Contract
Contract?
Interest to the DNFSB
(May 4, 98)
(May 98)
DOE O 430.1
Life Cycle Asset
No*
X
Upon meeting implementation conditions of this order, the
Management
following orders will be canceled: 1332.1A, 4010.1A,
4300.1C, 4320.1B, 4320.2A, 4330.4B, 4330.5, 4540.1C,
*Applies to DOE only
4700.1, 4700.3, 4700.4, 5700.2D, 6430.1A.
Implementation of Life Cycle Asset Management is
accomplished through actions:
C Establishment of DOE expectations with attendant
contractor performance measures - App F is used for this
purpose at LANL.
C Incorporation of primary expectations in the contract -
these expectations are found in the ?Functional
Requirements Documents.? The FDRs were written by
the functional program managers for the five Facilities
Management functions: site planning, project
management, maintenance, utilities, and real property.
Yes
Cancels 3790.1B except Chap VIII, 5480.7A, 5480.8A,
DOE O 440.1
Worker Protection
5480.9A, 5480.10, 5480.16A, & 5483.1A.
Management for DOE
Federal and Contractor
Employees
Addressed by parts of this Order plus other WSS.
Only Attach 1, para 3, Firearms Safety; para 6, Pressure
Safety Requirements; and Attach 2, para 13, Construction
Safety.
|