5.3 General Guidance 
a. 
Field Element Notification Requirements. Each field 
element plan should provide the following: 
DOE 5500.2B 
(1) A mechanism to ensure that all appropriate event 
_______________ 
12.b.(1) 
information from the affected facility is 
transmitted and received in accordance with DOE 
Orders 5500.2B and 5000.3B and that verbal 
notification and follow-on reporting of emergency 
events via secure communications, if necessary, 
are made to the HQ EOC. 
DOE 5500.2B 
(2) A mechanism to ensure that appropriate 
_______________ 
12.b.(2) 
information is provided to the regional Federal, 
state, tribal, and local authorities. 
DOE 5633.3 
(3) Notification to the local FBI office whenever an 
_______________ 
I.4.f 
abnormal situation indicates a loss of material 
and for which evidence of a malevolent act exists. 
DOE 5500.2B 
b. Headquarters Notification Requirements. The HQ 
12.a.(1),(2) 
emergency plan should be supported by procedures 
for the HQ EOC to: [Note: this element is not 
applicable to facility and field office plans.] 
(1) Record incoming verbal notifications, receive 
_______________ 
emergency event information by other data 
transmission means or mechanisms, and 
disseminate such information to appropriate HQ 
organizations and other federal agencies. 
(2) Facilitate communications among HQ 
_______________ 
organizations, DOE field organizations, and 
contractor personnel. 
36 
 | 
| 
 