| DOE-HDBK-5504-95
Source
Applicability &
Reference
Plan Element
Plan Reference
29 CFR
1910.38(a),
b.
The emergency plan should be supported by
1910.96(f),
procedures assuring timely sheltering and/or
1910.165(b),
evacuation of workers, including predetermined
1910.120(q)(2)(
guidance, procedures, assembly areas,
iv-vi);
transportation methods, and routes. These
40 CFR
procedures should include:
264.52(f);
DOE 5500.3A
(1) Identification of conditions that may require
11.c.(6)(c);
emergency actions to protect workers;
EMG-F/C 7.4;
______________
EMG-EXEC
(2) Provision for promptly warning workers of the
Crit. 3.1,
emergency, so as to allow time for protective
3.5;
action, including:
EMG-PA
______________
C.4, C.5.a;
(a) An alarm system capable of being
EMG-FE E.3.a,
perceived above ambient noise or light
E.3.d, E.6
levels by personnel in the affected area;
______________
(b) An alarm signal that is distinctive and
recognizable as a signal to take protective
action; and
______________
(c) Procedures for activation of the alarm
system.
(d) In areas where radiation hazard may
______________
require immediate evacuation, an alarm
system conforming to the requirements of
______________*
OSHA requirements 29 CFR
1910.96(f)(1-3), including automated
activation, backup power supply,
reliability, and testing regime.
(3) Provision for carrying out protective measures,
including:
(a) As appropriate, designated shelter areas,
______________
capacities, and circumstances for use.
______________
51
|