EXAMPLE 4-11. Time-dependent action steps.
NOTE
The following action step starts a time-limited sequence. Action steps [2] through
[5] are to be performed within 20 minutes.
[1]
Calculate the time by which action step [5] is to be completed by the following steps:
[a]
Record the time that action step [2] is to be started.
[b]
Add 20 minutes.
+
20 minutes
[c]
Record the time that action step [5] is to be completed.
Complete by
Place the Incident Action switch to TEST.
[2]
[3]
Verify the amber ALARM TEST light on the AIA graphic panel is LIT.
IV
[4]
Place the Incident Action switch to OFF.
[5]
Push the RESET pushbutton on the AIA logic tester and record the time.
[6]
IF the time recorded in action step [5] is later the time recorded in action step [1] [c],
THEN REPEAT action steps [1] through [5].
[4]
A note advising of time-dependent actions and instructions to record the time
information are not required when the time requirement is an inherent part of the
action step and misunderstanding is unlikely.
EXAMPLE 4-12. Time-dependent action step.
[1]
Push Generator Start pushbutton, and verify that the Generator started within 12 seconds.
Time to Start
Initial
IV
44