| DOE-STD-1038-93
2. OBJECTIVE
The objective and criteria are derived from DOE Order 5480.19. They are intended to aid
each facility in meeting the intent of the order.
Turnovers that provide on-coming personnel with an accurate status of their work stations are
systematically performed.
Criteria:
a. Supervisory personnel and specified work station operators use a checklist in the turnover
process.
b. On-coming personnel review specified documents prior to assuming responsibility for the
work station.
c. Walkdowns of appropriate control panels are conducted by on-coming personnel.
d. A discussion of facility status occurs between off-going and on-coming personnel prior to
transferring work station responsibility.
e. On-coming supervisors conduct personnel briefings as required.
f. Turnovers occurring during the shift are as thorough as necessary to ensure a complete
transfer of work station information.
3
|