| DOESTD107393
The Configuration Management Coordinator is responsible for:
-
selecting the walkdown teams and ensuring that team members have appropriate
background experience and training to be qualified to perform their role in walkdowns;
-
supervising the activities of the walkdown teams;
-
reviewing and approving the CCD sheets for completeness;
-
transmitting completed and approved CCD sheets to the Equipment Database
coordinator for inclusion into the Equipment Database; and
-
initiating any follow up actions (e.g., work requests, re-walkdowns, drawing change
notices, NCRS, etc.). to resolve discrepancies, including soliciting approval from the
design authority
The Equipment Database coordinator is responsible for:
-
obtaining the CCDs from the Configuration Management Coordinator, and
incorporating this data into the Equipment Database; and
-
providing the Configuration Management Coordinator with a printout for any
components within a system that have not been field verified after the system
walkdown has been completed. The objectives are to ensure that a component has
not been missed during the walkdown and that the CCD sheets have been properly
submitted and the information included in the Equipment Database.
The QA/QC group is responsible for:
-
reviewing the methodology and procedures used to field verify component data;
-
periodically inspecting the walkdown work in progress to ensure that it conforms to the
approved procedures and that an acceptable level of accuracy is achieved;
-
identifying and tracking to completion QA/QC discrepancies; and
-
working with the Configuration Management Coordinator and walkdown teams to
resolve any identified deficiencies.
8.0
INSTRUCTIONAL GUIDANCE.
All individuals associated with the component as-bulk configuration walkdown effort will be
trained on this procedure prior to conducting the verification walkdowns.
Each walkdown team will consist of at least two individuals experienced in the use of
applicable drawings (e.g., P&IDS, electrical single-line drawings and schematics, etc.). Prior
to each walkdown, the walkdown team will obtain and use the latest approved revisions of
the applicable drawings from the master file maintained by the Document Control Group.
II-C-6
|