Click here to make tpub.com your Home Page

Page Title: Change Control Element
Back | Up | Next

Click here for thousands of PDF manuals

Google


Web
www.tpub.com

Home

   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Logistics
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
   
   

 



DOESTD107393
2.4 CHANGE CONTROL ELEMENT
The development of the change control element is discussed below in two stages: the initial
development activities and the fully developed program element. The initial development activities
include those actions necessary to identify and evaluate existing change mechanisms. The fully
developed program element entails the activities involved in ongoing, steady-state change control.
2.4.1 INITIAL DEVELOPMENT ACTIVITIES
Major change mechanisms and immediate actions to improve change control will have been identified
by the initial program assessments and described in the CM program plan. This serves as the starting
point for a complete review of existing change mechanisms or processes. During this evaluation,
corrective actions should be Initiated promptly where necessary to prevent unauthorized, unreviewed,
improperly controlled, and poorly documented changes. An overview of the initial development
activities is presented as Figure 213, and these activities are discussed in more detail below.
2.4.1.1 Change Process Identification
A survey should be conducted to identify each change source (such as operations, maintenance,
procurement, procedures, and software) for each major change type (physical changes, document
changes, or design changes resulting in either). Facilities should focus on each change type (physical,
document, or design) individually to determine which sources initiate these changes and which
mechanisms are used to identify, evaluate, and control these changes. Input from each facility
organization should be solicited to identify the change sources and the control processes currently in
use. All change sources, mechanisms, organizations, and control processes that can possibly affect
configuration management should be identified. The identification of change processes is often the
most critical step to achieve effective change control. Change mechanisms that are not identified
cannot be controlled.
Facility personnel should strive to identify subtle change sources that do not conveniently fall in one of
the previously identified sources. Some change mechanisms exist independent of formal procedures
or processes. For example, if the system engineer approves minor changes such as different gaskets,
this should be identified and reviewed as a change source. Mechanisms for temporary physical
changes and temporary document changes should be identified for formal change control.
2.4.1.2 Change Process Evaluation
After the various sources of change have been identified, a determination should be made regarding
which of those processes after the configuration and therefore need formal controls. Formal control
measures should be provided for any change process that affects either (1) the physical configuration,
as defined by the SSCs included in the CM program or (2) the facility documents included in the CM
program. An example of a change mechanism that might be out of scope is the control of scaffolding
that cannot affect an SSC within the CM program (i.e., no system interaction through failing, etc.) or its
associated documentation.
The adequacy of the existing controls should be evaluated against each of the basic change control
functions, depicted in Figure 214 and described in Section 2.4.2. Checklists may be used to ensure
that the evaluations are complete and documented. Any weaknesses or deficiencies should be
identified. For example, if operations or maintenance personnel make undocumented changes to the
facility, existing controls are not adequate and do not meet the objectives of the CM program. Similarly,
if operations or maintenance personnel make changes without considering and documenting whether
II-39


Privacy Statement - Press Release - Copyright Information. - Contact Us

Integrated Publishing, Inc. - A (SDVOSB) Service Disabled Veteran Owned Small Business