|
| DOESTD107393
CHAPTER 4
IMPLEMENTATION GUIDANCE FOR
MATERIAL CONDITION AND AGING MANAGEMENT
This guidance is appropriate for high-hazard facilities expected to operate for an extended period.
Since DOE facilities vary in hazard level and circumstances of operation, a graded approach to
implementation should be adopted.
As shown in Figure 41, Material Condition and Aging Management (MCA) activities are developed and
implemented in three distinct phases: a preliminary phase, a detailed or main phase, and an ongoing
phase. The preliminary MCA phase includes activities necessary to estimate the facility remaining
lifetime and to develop the MCA program plan. The detailed MCA phase builds on the preliminary
estimate of facility remaining lifetime with more rigorous evaluations of aging degradation mechanisms
to determine more precisely the remaining lifetime. The detailed MCA phase also identifies life
extension techniques, if the facility desired lifetime is greater than the remaining lifetime. The ongoing
MCA phase identifies degradation measurements to be performed periodically for life-limiting
components, performs trending analyses on the results of those measurements to predict the end of
life, and implements any necessary life extension techniques. The results of the MCA activities are
reviewed by the design authority to determine whether there are new design requirements that should
be integrated into the ongoing configuration management (CM) program efforts.
4.1 PRELIMINARY MCA PHASE
The preliminary MCA phase has two primary objectives: (1) to develop a preliminary estimate of the
facility remaining lifetime and (2) to develop an appropriate MCA program plan.
4.1.1 COMPONENT SCREENING
Some components are so expensive or difficult to replace that their failure may limit the life of the
facility. The first activity in the preliminary MCA phase is to screen all components associated with the
facility, both active and passive (e.g., structural) components, to identify potentially life-limiting
components. They are to be categorized as mission structures, systems, and components (SSCs) if
they do not warrant a higher category and are to be addressed in the overall CM program.
The first step is to identify all components associated with the facility, both active components and
passive components, including structural components. A typical facility may encompass hundreds,
even thousands, of individual components. To provide reasonable assurance that all facility
components are considered and none are inadvertently overlooked, the preferred approach is to use a
Master Equipment List (MEL) if the facility has one. If not, the best available information should be
used, such as maintenance records, system design descriptions (if they exist), and engineering
drawings.
The next step is a review of these facility components by experienced personnel who have a detailed
knowledge of the facility and who can identify those components whose failure would have a major
cost, safety, or programmatic impact on the facility. This phase of the MCA program excludes
components that can be repaired or replaced. After consideration of several hundred components, a
small number (perhaps a dozen) are likely to emerge as potentially life-limiting for the facility.
II-85
|
Privacy Statement - Press Release - Copyright Information. - Contact Us |