1.3.3.3 Control and Tracking
Only the currently-approved revisions of documents within the CM program should be used. Revisions
to documents within the CM program to incorporate pending changes should be completed in a timely
manner. The number of unincorporated document changes allowed to accumulate before revisions
are implemented should be determined according to the priority of the document, the complexity of the
changes and the overlap of the changes. For each document within the CM program, the following
information should be readily available: revision level, current status, document owner, information
regarding pending changes, and other data necessary for control and tracking, such as storage
location and outstanding document change notices (DCNs).
1.3.3.4 Retrieval
Documents should be retrieved in a timely manner upon request. Maximum retrieval times for each
document should be established, and they should be based on the priorities established by the
document owners. Documents should be identifiable from a document database, which should be able
to identify documents within the CM program related to particular SSCs, types of SSCs, technical
topics, and other information to support identification, such as SSC vendors. When a copy of a
document within the CM program is issued, pending changes and associated information should be
identified.
The objective of the change control element is to maintain consistency among the design requirements,
the physical configuration, and the facility documentation as changes are made.
1.3.4.1 Identification of Changes
All mechanisms that can lead to temporary or permanent changes in the design requirements, facility
configuration, or facility documentation within the CM program should be identified. Such mechanisms
might include hardware modifications not controlled as projects, hardware modifications controlled as
projects, maintenance changes, operational changes, procurement changes, document changes, and
computer software changes. Change mechanisms should be evaluated to determine which are
adequate as is, and which need to be improved, consolidated, or terminated. The resulting change
mechanisms should be integrated with the CM program. Within approved CM change mechanisms,
each proposed change, including temporary changes and partially implemented changes, should be
described sufficiently to support technical reviews, management reviews, and approvals.
1.3.4.2 Technical Review of Changes
Each specific proposed change should be reviewed to determine if it is within the bounds of the design
requirements. Changes to the design requirements should be evaluated and approved by the design
authority prior to implementation. The technical reviews should evaluate safety, environmental, and
mission impacts; determine appropriate post-implementation acceptance criteria; and identify the
affected SSCs and facility documentation.
1.3.4.3 Management Review of Changes
Before implementation, management should review proposed changes (including those that do not
involve a change to design requirements) to verify that the technical reviews have been performed
adequately, that the change package is complete and ready for implementation, and that any external