Click here to make tpub.com your Home Page

Page Title: Design Basis vs. Design Requirements cont'd
Back | Up | Next

Click here for thousands of PDF manuals

Google


Web
www.tpub.com

Home

   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Logistics
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
   
   

 



DOESTD107393
generated by the engineering organization and approved for construction; from an operator's viewpoint,
design requirements might be a combination of these other views.
Because the DOE operational CM program focuses on the operational life-cycle phase, it is oriented
more toward the operating organizations (which includes maintenance and testing) than the facility
design or construction organizations. From this context, a DOE operational CM program defines design
requirements as the output requirements the design organization has placed on the facility
configuration. In contrast, incoming requirements to the design organization are design inputs.
Historically, changes were made to the facility hardware at some commercial nuclear facilities without a
full recognization that the design was being changed. Heightened industry awareness led to an
appreciation that hardware changes were, in fact, design changes that needed careful evaluation and
prior approval. Everything involved with the design of the physical hardware was considered to be the
basis for the physical design, including the functional requirements, the physical characteristics, and the
required performance capabilities, as well as the underlying calculations and analyses. Many nuclear
utilities developed summary design documents, which they called Design Basis Documents, describing
both what is required and why it is required. The term "design basis" was used to support the central
concepts that physical changes are design changes and that an appreciation for the basis of the
physical design is necessary. However, this usage of the term design basis lacked accuracy.
As commercial nuclear and DOE experience accumulates, it has become apparent that the physical
design does not actually conform with the design basis. Rather, the physical design matches the
design output requirements. The design basis, in turn, provides the information demonstrating that the
design output requirements are appropriate. To take advantage of this improved understanding, this
Standard adopts refined definitions for design requirements and design basis. In simple terms, the
design requirements specify what is required and the design basis explains why it is required. The total
set of design requirements and design basis is referred to as the design information.
The following example illustrates the difference between design requirements and design basis. A
design has been requested for a safety heat removal system. The design inputs might state that the
system needs to provide at least 165 gpm of light water with a temperature no greater than 80 F into a
system that is pressurized at 125 psig. The origin for this design input might have been a worst-case
accident heat removal calculation. The pump sizing calculation might be performed according to a
defined engineering procedure for pump sizing. From these design inputs, constraints, analysis and
calculations, the design outputs might specify a centrifugal pump with a 200 gpm rating at 150 psig.
For this example, the requirement for 165 gpm at 80 F into 125 psig is a design input. However, the
pump design requirement specifies a 200 gpm pump at 150 psig. The difference might have come out
of calculational uncertainties or specified design constraints, or it might be a reflection of the
conservative margin employed by the designer. Regardless, the design requirement is 200 gpm at 150
psig. In addition, the nameplate rating of the pump purchased to meet this requirement might exceed
the design output requirement, thus providing an additional margin. In a different case, the design
output might be identical to the design input. The design process, through its constraints and analysis
and calculations, does not always result in a change of the original design input.
As a matter of good practice, design requirements are best specified as the minimum acceptable value,
without excessive built-in design margin. For example, a design analysis determines that a 200 gpm
pump is needed to meet system requirements, but the vendor can only supply a 250 gpm pump. The
pump design requirement is best established at 200 gpm because this is the value the designer
determined is needed to satisfy the system design requirements. The procurement specification might
state the 200 gpm design requirement and request the 250 gpm pump that is available to satisfy it. The
200 gpm value is preferred as the specified design requirement because it tends to minimize
I-B-6


Privacy Statement - Press Release - Copyright Information. - Contact Us

Integrated Publishing, Inc. - A (SDVOSB) Service Disabled Veteran Owned Small Business