|
| DOESTD107393
operational CM program appropriate for a high-hazard facility that is expected to operate for an
extended period. Section 1.4 describes the graded approach for applying these program criteria to
other facilities and situations.
The Glossary provides descriptions of key terms used in these program criteria and throughout this
Standard. Appendix I-B provides background material and concepts that establish the context in which
this Standard should be understood.
The objective of the program management element is to direct and monitor the development and
implementation of the overall CM program.
1.3.1.1 Program Planning
The CM program developed and Implemented by a contractor authorized to manage or operate a
DOE-owned facility should reflect appropriate consideration of the guidance contained in this Standard.
A graded approach (described in Section 1.4) should be used to determine the depth of detail
necessary and the magnitude of resources to be invested in each CM program function. Configuration
management program planning should include the following:
a.
Issuance by the DOE prime contractor of a site/division-level CM policy directive that announces
top management support for the CM program, defines key roles and responsibilities, provides
criteria for the CM equipment scope, and establishes key terminology and definitions.
b.
Initiation of immediate corrective actions for substantive weaknesses discovered during the initial
assessments (as described in criterion 1.3.5.1.a).
c.
Development of the CM program plan, based on the graded approach and initial assessments,
that defines the appropriate level of implementation for specific facilities, describes those actions
already taken to develop and implement the CM program, and identifies the schedules and costs
associated with those actions. This plan should address each of the following topics: scope of the
structures, systems, and components (SSCs) to be included in the CM program; objectives of
each program activity; description of each program activity; basis for the technical content of each
program activity; organizational structure and staffing; interfaces; implementation priorities,
milestone deliverables, and implementation schedules; and cost estimates. The CM program
plan for the basic CM program elements should be provided for DOE review within 18 months
after program planning is initiated. The DR and MCA adjunct program plans may be provided
separately from the CM program plan, but they should be provided within an additional 6 months
after the CM program plan is provided, and they should be incorporated as a part the CM program
plan.
1.3.1.2 Equipment Scope Criteria
The types of equipment to be included in the CM program should be identified. The equipment scope
of the CM program should be based on the functions provided by the SSCs and should include those
SSCs involving safety design requirements (those necessary to protect off-site personnel, on-site
personnel, and facility workers from nuclear and other hazards), environmental design requirements
(those necessary to protect the environment from significant damage or to satisfy environmental
requirements or permits), and mission design requirements (those necessary to avoid substantial
interruptions of the programmatic mission or severe cost impacts).
I-6
|
Privacy Statement - Press Release - Copyright Information. - Contact Us |