Click here to make tpub.com your Home Page

Page Title: Appendix E: Example Vibration Monitoring Program Procedure
Back | Up | Next

Click here for thousands of PDF manuals

Google


Web
www.tpub.com

Home

   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Logistics
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
   
   

 



DOE-STD-1052-93
APPENDIX E
EXAMPLE VIBRATION MONITORING PROGRAM PROCEDURE
1.1 Identification of Monitored Equipment
1.1.1 The predictive maintenance coordinator should maintain a listing of plant equipment
included in the predictive maintenance vibration monitoring program. This listing
(Appendix E, Table 1 of this procedure) should contain the following information on
each piece of equipment:
a. component tag number and description
b. priority
c. interval of monitoring
NOTE:
For purposes of this good practice. Table 1 illustrates only a small
portion of the equipment included in the vibration monitoring program.
1.1.2 Specific points to be monitored on each machine should be designated by the
predictive maintenance coordinator. Each point should be marked on the machine in
a conspicuous manner (e.g., by using a paint or ink-marking device) to help ensure
that data is taken in a consistent manner. Permanently mounted pick-up pads also are
an effective method for ensuring consistent data.
1.1.3 Upon request from members of plant management or in support of other
maintenance activities, data may be taken on equipment other than that listed in
Table 1.
1.2 Scheduling of Vibration Surveys
1.2.1 Equipment should be scheduled for vibration testing at the frequency indicated in
Table 1. Readings may be taken more frequently at the discretion of the predictive
maintenance coordinator or as requested by plant staff. Vibration baseline readings
should be taken after any maintenance affecting the rotating components of the
machinery, such as bearing replacements. In addition, vibration data on selected
plant equipment may be useful prior to securing the equipment for a planned outage
to allow for repairs.
1.2.2 Equipment not in operation at the time of a scheduled test should not be started for
the sole purpose of obtaining vibration readings unless justified. Such vibration tests
should be rescheduled to a time consistent with normal plant and equipment
operations, but within vibration test interval.