| DOE-STD-1054-93
c)
Determine new technology and its potential for adding value to applications if
acquired
3.2 S cope
This guideline applies to M&TE used on safety class items, as well as, safety-related
structures, sy stems, and components (SSC) or on SSC which affects critical plant
performance and reliability.
3.3 Res ponsibilities
3.3.1
M&O Operators
It is the responsibility of each M&O Operator to ensure that M&TE for their
group has a current calibration sticker prior to use.
Plant Personnel
3.3.2
Plant personnel using M&TE should be responsible for reporting any
malfunctions or suspected malfunctions to the cognizant department supervisor.
Personnel should ensure that the equipment calibration date has not expired. Refer
to Section 3.4.3.4.2 for appropriate action for equipment past the calibration due date.