23.
Managerial qualifications of contractor personnel, responsible for facility operations, are
adequate. (CR-19)
24.
Functions, assignments, responsibilities, and reporting relationships are clearly defined,
understood, and effectively implemented with line management responsible for control of
safety. (CR-11)
25.
A process has been established to identify, evaluate, and resolve deficiencies and
recommendation made by oversight groups, official review teams, audit organizations, and the
operating contractor. (CR-6)
26.
A systematic review of the facility's conformance to applicable DOE Orders has been
performed. (CR-7)
27.
Non-conformances to applicable DOE Orders have been justified, and schedules for gaining
compliance have been justified in writing and formally approved. (CR-7)
28.
An adequate startup or restart test program has been developed that includes adequate plans
for graded operations testing to simultaneously confirm operability of equipment, the viability
of procedures, and the training of operators. (CR-10)
29.
A program is established to promote a site-wide safety culture. (CR-14)
30.
The breadth, depth and results of the responsible contractor Operational Readiness Review are
adequate to verify the readiness of hardware, personnel, and management programs for
operations (DOE Operational Readiness review only). (CR-17)
31.
Technical and managerial qualifications of the DOE field organization personnel assigned
responsibility for providing direction and guidance to the contractor, including the Facility
Representatives, are adequate (DOE only). (CR-16)
Appendix 2-9
|