| DOE-STD-3006-95
5.3 Roles and responsibilities for DOE Headquarters. This section is divided into two parts.
The first (5.3.1) describes the roles and responsibilities of DOE Headquarters Line Management
personnel. The second part (5.3.2) describes the roles and responsibilities of the DOE Headquarters
Independent Oversight personnel (Office of Environment, Safety, and Health). The second part also
describes the conflict resolution process by which comments developed by the independent oversight
organization (EH) are resolved. One key purpose for the structured conflict resolution process is to
insure that resumptions are not delayed due to unresolved differences of opinion between line
management and EH.
5.3.1 Headquarters DOE Management. The following items are a summary of the
responsibilities of the Secretarial Officer. The specific items are further defined in other sections of
this standard or in DOE 0 425.1. The summary provides a listing which responsible managers can
use to verify that all necessary steps and decisions have been considered.
5.3.1.1 Obtain Secretary of Energy Approval. The Secretarial Officer must gain S-1 approval in
the following situations for startup or restarts of nuclear facilities when S-1 is the approval authority.
5.3.1.2 Implementing Procedures. Prepare implementing procedures as necessary to carry out the
requirements of the readiness review process in accordance with the requirements of DOE 0 425.1 and
the principles of this standard. In those cases where the Secretarial Officer intends to delegate the
approval responsibility for specific actions or individual circumstances, the delegation should be
specified in the implementing procedures to be provided by formal letter or memorandum.
5.3.1.3 Approve Responsible Contractors Startup Notification Report. This report should be
received periodically from each responsible contractor with recommended actions by the Operations
Office manager. DOE Headquarters management should receive and approve it, or approve with
modifications. Copies of the approved report are returned to the responsible contractor via the
Operations Office with additional copies sent to all interested internal and external oversight
organizations.
5.3.1.4 Approve the ORR Plan-of-Action. Each new start or restart will require both a
contractor and DOE ORR plan-of-action. Since each new start or restart is unique, the plan-of-
33
|