Click here to make tpub.com your Home Page

Page Title: Drill Team Preparation
Back | Up | Next

Click here for thousands of PDF manuals

Google


Web
www.tpub.com

Home

   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Logistics
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
   
   

 



DOE-HDBK-1099-96
APPENDIX B - EXAMPLE DRILL SCENARIOS
Title:
Evaporator Feed Tank Header Line Leak
Drill Number:
WEACDC04
Revision Number: 0
6. Ensure each drill team member notes, on a drill chronology log, all actions or events
observed during the course of the drill, to include pertinent comments.
7. Upon termination of drill, return all facility equipment and systems to the required pre-drill
state.
8. Discuss crew performance with drill team members.
9. Coordinate a formal drill critique with the drill participants.
10. Complete a drill summary and route to all required personnel.
DRILL TEAM PREPARATION
Estimated Drill Duration:
2 hours
Drill Team Aids:
Props and equipment required:
Process water hose placed over piping and running to simulate leak rate and a blue
ribbon to indicate leak location.
Pre-drill Notifications:
The Drill Coordinator is responsible for making the following notifications prior to initiating drill:
NOTE:
Unannounced drill do not require notifications, but courtesy notifications are
suggested.
Unannounced drills require no pre-drill announcement.
1. Request ETF Control Room (X-XXXX) make the following pre-drill announcement:
"The Effluent Treatment Facility will be conducting facility drills. Please keep non-essential
radio traffic to a minimum."
2. Inform Radiological Controls (X-XXXX) of scheduled drill activities.
Pre-drill Briefing (Conducted by Drill Coordinator):
Activities of Drill Coordinator:
B 6-3


Privacy Statement - Press Release - Copyright Information. - Contact Us

Integrated Publishing, Inc. - A (SDVOSB) Service Disabled Veteran Owned Small Business