| DOE-HDBK-1188-2006
considered applicable power plant experience and should be evaluated on a case-by-case
basis. [DOE O 5480.20A]
469.
PREDICTIVE MAINTENANCE. Predictive maintenance consists of the actions necessary to
monitor, find trends, and analyze parameters, properties and performance characteristics or
signatures associated with structures, systems, and components (SSCs), facilities or pieces of
equipment to discern whether or not a state or condition may be approaching which is indicative
of deteriorating performance or impending failure, where the intended function of the SSCs,
facilities or pieces of equipment may be compromised. Predictive maintenance activities involve
continuous or periodic monitoring and diagnosis in order to forecast component degradation so
that "as-needed" planned maintenance can be initiated prior to failure. Not all SSC, facility or
equipment conditions and failure modes can be monitored and diagnosed in advance; therefore,
predictive maintenance should be selectively applied. To the extent that predictive maintenance
can be relied on without large uncertainties, it is normally preferable to activities such as periodic
internal inspection or equipment overhauls. [DOE G 433.1-1]
470.
PRELIMINARY DOCUMENTED SAFETY ANALYSIS. Documentation prepared in
connection with the design and construction of a new DOE nuclear facility or a major
modification to a DOE nuclear facility that provides a reasonable basis for the preliminary
conclusion that the nuclear facility can be operated safely through the consideration of factors
such as
A. The nuclear safety design criteria to be satisfied;
B. A safety analysis that derives aspects of design that are necessary to satisfy the nuclear
safety design criteria; and
C. An initial listing of the safety management programs that must be developed to address
operational safety considerations.
(See Final Safety Analysis Report, Preliminary Safety Analysis Report, Safety Analysis Report,
Safety Basis, Safety Evaluation, and Safety Evaluation Report) [10 CFR 830.3]
471.
PRELIMINARY NOTICE OF VIOLATION. A document issued by the Director in which
the Director sets forth the preliminary conclusions that the respondent has violated or is
continuing to violate a DOE Nuclear Safety Requirement and includes:
(i)
A statement specifying the DOE Nuclear Safety Requirement to which the violation
relates;
75
|