Click here to make tpub.com your Home Page

Page Title: On-Site ORR Responsibilities
Back | Up | Next

Click here for thousands of PDF manuals

Google


Web
www.tpub.com

Home

   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Logistics
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
   
   

 



DOE-HDBK-3012-2003
Make arrangements to mail data packets to team members. Packages should be delivered to team
members at least two weeks before the beginning of the ORR. If possible, arrange for electronic or
computer disk distribution of current site and facility documents.
Keep the site point-of-contact informed of any team member/schedule changes by updating and faxing the
team member assignment chart. Make sure latest date is on the chart.
Keep all team members informed of the status of progress and potential or actual changes in ORR start
dates.
Prepare a package to mail to hotel and to have available at the initial team meeting. The package should
include any information and/or documents the Team Leader and DOE-HQ team members need for the
ORR, such as the standard format used and examples from previous reviews; latest agendas and
schedules; computer disks with all ORR information; blank Forms 1 and 2; previous ORR closeout
summary examples; and the template for the word processing software to be used. The package must be
provided to each team member no later than the first team meeting at the beginning of the ORR.
Encourage the site to provide electronic access to information required by the team members. As an
alternative, many sites can provide documentation on a computer disk. Getting the information on
computer disk has worked well in several recent reviews.
4.0 THE ORR
The ORR will not start until the Team Leader has received the formal direction to start the ORR from the
Authorization Authority or senior contractor manager. This formal direction means that all prerequisites
for starting the ORR have been met and that readiness to commence operations has been achieved.
4.1 ON-SITE ORR RESPONSIBILITIES
4.1.1. TEAM LEADER RESPONSIBILITIES
 Ensure all team members have completed all access requirements of the site.
 Hold daily team meetings (usually held in the afternoon) to discuss emerging issues. Functional Area
Leaders, if assigned, or team members brief the Team Leader on the issues uncovered during the day
(this is not intended to be a travelogue of the day's events). Issues deemed sufficiently substantive by
the Team Leader will be identified as potential findings and may be drafted onto Form 2s. Some
duplication of effort is to be expected and it can often lead to beneficial cross-talk and fuller
understanding of the issues. Issues raised may be assigned to a different functional area or sub-team
if it is felt that better coverage will result. The Team Leader resolves any disputes between functional
areas or sub-teams that occur. Additional guidance for the conduct of the ORR can be found in
section 5.4.6 of the ORR Standard.
 Invite the site to have observers (not a participant) at the team meeting to hear first hand the team
issues and concerns. Remind team members that their counterparts should be kept aware of the
emerging issues.
 Meet frequently (daily is recommended) with site managers to brief them on the issues raised by the
previous day's review activities. The Team Leader discusses potential findings and other issues
uncovered during the previous day's activities. This greatly enhances site/team communication and
allows the site to better facilitate the validation process.
 Conduct the opening meeting at site. This meeting is the "kickoff" meeting for the commencement of
the ORR. Items to consider for completion during this meeting include:
10


Privacy Statement - Press Release - Copyright Information. - Contact Us

Integrated Publishing, Inc. - A (SDVOSB) Service Disabled Veteran Owned Small Business