| DOE-HDBK-1078-94
Primary Cooling System Operations--Single-Loop and Natural Circulation
Scenario Title:
Operations.
Classroom Preview--2 to 4 h
Setting/Duration:
Control Room Simulator--2 to 4 h.
References:
1.
ECCS Surveillance
a.
Plant Procedure 7.4.5.17, Emergency Core Cooling System (ECCS) Surveillance and
associated data sheets
b.
Plant Procedure 2.13, Emergency Core Cooling System
c.
Technical Specification (TS) 3/4.5.1.
2.
Primary Cooling Pump Seal Failure
a.
Plant Procedure 4.3.1.2, High Unidentified Reactor Leakage
b.
Plant Procedure 4.3.1.3, High Identified Reactor Leakage
c.
Plant Procedure 4.2.1.7, Primary Cooling Pump Seal Failure
d.
Technical Specifications 3/4.3.2, 3/4.1.1, and 3/4.4.1.
3.
Primary Cooling Pump Trip
a.
Annunciator Procedure 4.602.A13-4.5 Primary Cooling Pump Turbine Trip
b.
Annunciator Procedure 4.602.A6-4.7 Primary Cooling Pump Trip.
Malfunctions:
1.
10-05-0001 Primary Cooling Pump "A" Seal Failure
2.
10-01-0002 Primary Cooling Pump "B" Turbine Trip.
Initial Conditions:
1.
IC-11 [100% power, end of life (EOL)]
a.
Core thermal power--2425MW(t) (99.55%)
b.
Core flow--102M lb/h (99.55%)
138
|
Privacy Statement - Press Release - Copyright Information. - Contact Us |