| DOE-HDBK-1099-96
APPENDIX B - EXAMPLE DRILL SCENARIOS
Title:
Evaporator Feed Tank Header Line Leak
Drill Number:
WEACDC04
Revision Number: 0
Established entry requirements for spill area.
Contaminated materials were disposed of
IAW 5Q Manual
POST-DRILL ACTIVITIES
FACILITY RESTORATION
Restore all facility equipment and systems to their required pre-drill state and perform an
independent verification to ensure completion.
Return process water hose to original location, if used.
Return Evaporator Sump Pumps to "Auto," if applicable.
POST-DRILL NOTIFICATIONS
The Drill Coordinator is responsible for notifying the following that the ETF drill is complete:
ETF control room (X-XXXX), request the following post-drill announcement: "The Effluent
Treatment Facility has completed facility drills."
POST-DRILL DISCUSSION
Discuss with the crew, short and long range impact on facility conditions resulting from the given
scenario.
Alternate ways of pumping sumps until repairs are completed.
B 6-8
|