Exhibit 2.6.1
DOE-HDBK-1101-96
4. Validation
Data submitted should be revalidated to ensure that it applies to the local subcontractor
and not to it's parent company or an affiliate.
B.
Pre-Bid
The DOE contractor shall inform subcontractors of the facility's safety requirements by
clearly outlining safety performance requirements in its bid package, which will be used
as part of the selection process.. The DOE contractor shall request specific safety
information from the subcontractor to compare with qualification criteria to establish
contractor responsibility. The subcontractor should be advised of the qualification
criteria and that the lowest bid might not be selected.
1. Subcontractor Suitability to Bid
Once the scope of work has been defined, the DOE contractor will request that
subcontractors selected to bid submit all safety management program information
necessary to establish contractor suitability.
2. GOCO Facility Safety and Health Qualification Criteria
The DOE contractor shall clearly outline safety and health requirements in the bid
package. The items contained in the Subcontractor's Safety Questionnaire (Exhibit 2.6.2)
should be included, along with any site specific safety and health rules that might apply.
These requirements shall be consistent with the requirements the DOE contractor has for
its own employees.
3. Contract Safety Language
Standard safety language ("the subcontractor must comply with all federal, state, and
local safety laws and regulations") shall be included in contracts. Also, safety and health
requirements specific to the GOCO facility and the work being performed shall be
included in the contract as a separate addendum.
4. Pre-bid Meeting
The DOE contractor shall hold a pre-bid meeting to discuss facility safety and health
requirements. Subcontractors shall be provided copies of any applicable facility safety
and health policies and procedures. This meeting shall also establish who provides the
required safety and health equipment and training, and shall define subcontractor
documentation requirements.
C.
Selecting Subcontractors
1. Considerations
The DOE contractor shall review each subcontractor's Safety Questionnaire, along with
the requested material, for thoroughness and ability to meet or exceed the facility's
minimum safety and health qualification criteria. The subcontractor's ability to safely
perform the specified work should be a significant factor, along with cost, quality and
time. The reasoning used to select the subcontractor must be documented.