|
| DOE-HDBK-1129-99
The TRL used approximately 100 oil-type vacuum pumps. Oil-free vacuum pumps were not as
common when the TRL was designed. The vacuum pump oil becomes contaminated with
tritium during use. At some DOE locations, tritium-contaminated oil is regulated as a mixed
waste. Handling the tritium-contaminated oil is a significant safety hazard to operating
personnel and should be eliminated where practical.
If oil-free vacuum pumps had been used, the generation of mixed waste in the form of tritium-
contaminated vacuum pump oil would have been eliminated as would the hazard associated
with changing vacuum pump oil.
The TRL was equipped with a ten-air-change-per-hour, single-pass, pressure-zone-controlled
ventilation system. Some of the ductwork became contaminated and was removed and
disposed of as solid low-level (radioactive) waste during the transition process.
Experience from Sandia has suggested that if the ventilation ductwork for room air ventilation
had been separated from the ductwork used for high velocity air hood and glovebox ventilation,
the contamination would have been easier to control during the transition process.
The presence of hazardous materials in the form of asbestos and oil complicated the transition
process. The materials used in fabrication and during facility operation should be reviewed,
and, if possible, all hazardous materials should be eliminated.
The initial design of the TRL included collection of wastewater from floor drains and sinks in
two underground holding tanks so that the water could be checked for contamination before it
was sent for disposal. The holding tanks were buried and could not be inspected. The
wastewater drain system consisted of several hundred feet of buried drainpipe, which drained
into the holding tanks. After a few years of operation, the underground tanks were replaced
with holding tanks enclosed in a below-ground-level open concrete pit. If the tanks leaked, the
concrete pit would contain the leak. This design also provided for inspection of the tanks for
leaks. The buried, underground drain lines remained in place throughout the life of the facility.
Wastewater holding tanks and collection systems should be designed so that potential leaks
can be contained and the holding tanks and drain system can be inspected periodically.
4.6.2 SRS Old Tritium Extraction Facility
Between 1995 and 1997, a team of specialists decontaminated and decommissioned (D&D) the
Old Tritium Extraction Facility (232-F) at the SRS. [24] The work was conducted in six phases.
Each phase presented challenges regarding the behavior of tritium, particularly tritium in
equipment and structures of metal and concrete. A description of each phase is as follows:
Phase I, pre-Characterization/Isolation, was designed to identify the specific buildings, ancillary
equipment, structures and premises to be cleaned, and isolate them in a way that avoided
inadvertent contamination elsewhere in the complex.
Phase II, Detailed Facility Characterization, included determination of the type and amount of
actual contaminants and determined the location and type of disposal operations required.
This phase was the most complex in terms of characterizing tritium contamination.
45
|
Privacy Statement - Press Release - Copyright Information. - Contact Us |