|
| DOE-HDBK-1129-99
Tritium facility utilities such as chilled water, compressed air, gas supplies, ventilation, floor drains,
sink drains, storm drains, and stacks should not be shared with other non-tritium areas. Sharing
these systems spreads tritium contamination to other areas, complicates day-to-day management
of the facility, and impacts the transition process if the facility is transitioned to other use. The use
of hazardous materials should be reduced or eliminated in the initial design stages of the facility,
as it will likely lead to the generation of mixed wastes and increased D&D costs.
4.6.1 SNLL Tritium Research Laboratory
Tritium operations have been terminated at the TRL, and the facility has been transitioned to other
use. The problems encountered during transition of the TRL should serve as an example for
facility designers of the future. The TRL was designed beginning in 1972 specifically to handle
tritium, and a few changes to the initial design would have resulted in significant cost and
timesaving during the transition process.
The tritium removal system in the central glovebox had a supply and return manifold fabricated
of six-inch diameter stainless steel pipe. The associated vacuum pump effluent manifold
consisted of an all welded two-inch diameter pipe. These manifolds were approximately 200
feet long and extended down the central corridor of the building. The manifolds extended into
each room from the corridor and were of all welded construction. During the transition process,
special tooling had to be purchased to cut the six-inch and two-inch diameter pipe into sections
small enough to be disposed of as solid waste.
Designing the system to include flanges and isolation valves at specific locations would have
resulted in some cost savings during facility dismantlement and transition. However, since too
many valves and flanges can increase the potential for leaks during operation, the installation
points should be placed only at strategic locations.
The floor covering installed in the TRL consisted of 12-inch tiles glued to the concrete floor.
Both the floor tile and the adhesive contained asbestos that had to be removed during
transition of the facility. Additionally, tritium-contaminated liquids were spilled on the floor
during operation and leaked through the tile into the concrete below. The use of adhesives
made of non-hazardous materials would have resulted in significant cost saving.
Princeton University Plasma Physics Laboratory has suggested that sealing the concrete with a
thick, hard finish epoxy paint prior to installation of any floor covering would mitigate the impact
of tritiated liquid spills, although even epoxy will experience tritium permeation.
The TRL was equipped with a recirculating chilled water system. The water-to-gas heat
exchangers used the chilled water to cool the glovebox and vacuum effluent tritium removal
system gases, vacuum furnace heat exchangers, glovebox temperature control systems, and
in a variety of other tritium-related tasks. After a few months of operation, tritium
contamination was found in the chilled water. In order to control the buildup of tritium in this
system, the contaminated water was periodically drained from the system and replaced with
uncontaminated water.
If the initial design had used water-to-water heat exchangers as barriers, the volume of
contaminated water would have been minimized. If double-walled, gas-flushed, water-to-gas
heat exchangers had been used, the contamination would have been significantly lower.
44
|
Privacy Statement - Press Release - Copyright Information. - Contact Us |