| DOE-HDBK-3027-99
6.3.5 ISMS Combined Phase I and Phase II Verification Specifics
As discussed in Section 5.4, a combined verification should be conducted only when it is clear
that the site had achieved a mature implementation of the ISMS. The ISMS should also be
consistent with the system description that was submitted to the HCA for approval. It is possible
to conduct a combined verification when the implementation is not complete or mature in some
known areas but which is complete and mature in a majority of the areas. A combined
verification should not be attempted when all of the mechanisms for implementation of the ISMS
Description have not been developed or have not been implemented.
The ISMS verification team for a combined verification should contain members with previous
ISMS verification experience as well as a good understanding of the site and the work that is
conducted at the site. Experience with the site and the work conducted there is particularly
important for the members of the operations and SME sub-teams and some members of the
management sub-team. Each sub-team should have an experienced sub-team leader for a
combined verification.
For a combined verification, it is recommended the team and review be divided into the following
Functional Areas:
Business, Budget, and Contracts (Phase I)
+
Hazards Identification and Standards Selection (Phase I & II)
+
Department of Energy (Phase I & II)
+
Management (Phase I & II)
+
Operations and Implementation (Phase II)
+
Subject Matter Experts (Phase II)
+
The bulk of the Phase II portion of the verification is assigned to the Operations and
Implementation and Subject Matter Expert sub-teams. Some portion of the DOE and
Management assessment activities are also focused on implementation of the ISMS, although
more of their effort is focused on the Phase I aspect of the verification.
A major challenge to a successful combined verification is development of an effective and
efficient Review Plan. The Review Plan must be developed with a detailed understanding of the
site, facility, or activity. The draft or preliminary plan is normally developed by the Team Leader
or an individual who has been tasked by the Team Leader to prepare the draft Review Plan. The
draft is then further tailored by the individual team members. The development of the draft
Review Plan must occur with full and detailed knowledge of the site, facility, or activity, its
history including recent ORRs and other verifications and with an understanding of the work that
is accomplished, and an understanding of the procedures and processes that are utilized. The
verification must build from the history of the site, facility, or activity and look at the work
involved. The success of the verification will depend in large measure on the effectiveness of the
Review Plan. The draft CRADs for both a Phase I verification and a Phase II verification should
be included in the Review Plan. The CRADs must be tailored to reflect the work, the unique
aspects, and the history of the site, facility, or activity. The CRADs should also be tailored to
remove overlap and redundancy that exists with the CRADs that are designed for stand alone
23
|