| DOE-HDBK-5504-95
Planning Standard: Provisions must be made for and reentry into the affected facility and recovery from
an operational emergency. [5500.3A.11c(8)]
Evaluation Guidance:
Source
Applicability &
Reference
Plan Element
Plan Reference
9.1 Emergency Termination or Downgrade
DOE 5500.3A
An emergency plan should include the approach and general
11.c(8)(a);
procedures for recovery, including provisions for:
EMG-F/C
5.1,7.7,9.1
EMG-R/R
C.3.a
a.
Decision making and communications associated with
_______________
termination of an emergency. The plan should describe:
(1)
The conditions under which the emergency can be
_______________
EMG-F/C
considered over. (Note: the plan may reference
9.1
another document, such as EMG-R/R Sec. C.3.a,
that contains such conditions.)
(2)
The procedure for terminating or downgrading an
_______________
EMG-F/C
operational emergency, including the personnel
9.1
responsible for decision making and their
relationship to the overall emergency response
organization.
DOE 5500.3A
b.
Dissemination of information to Federal, state,
_______________
11.c(8)(a);
tribal, and local organizations regarding
DOE 5000.3B
termination of the emergency and, if appropriate,
7.c;
relaxation of public protective actions.
EMG-F/C
7.7;
EMG-R/R
C.3.c
|