| The criteria identified in this chapter address the ini-
tial and preoperational testing of systems, structures, and com-
ponents important to safety at nuclear reactor plant facilities.
This section in an SAR should describe the major phases
of the initial test program and the overall test objectives and
general prerequisites for each major phase.
In addition, it
should describe how the initial test program will be applied and
the organizations that will participate in the development and
execution of the test program.
No specific NRC criteria are
identified for this section.
14.2.1
Code of Federal Regulations
A.
10 CFR 30.53, "Tests."
B.
10 CFR 50.34, "Contents of Applications: Technical
Information," paragraph (b)(6) (iii), "Plans for Preoperational
Testing and Initial Operations."
10 CFR 50, Appendix B, "Quality Assurance Criteria
C.
for Nuclear Power Plants and Fuel Processing Plants," Section XI,
"Test Control."
D.
10 CFR 50, Appendix J, "Primary Reactor Containment
Leakage Testing for Water-Cooled Power Reactors," Section
III.A.4, "Preoperational Leakage Rate Tests (Type A Test)."
14.2.2
USNRC Regulatory Guides, SRP Branch Technical Positions
and Appendices
A.
Regulatory
Guide
1.18, "Structural Acceptance
Test for Concrete Primary Reactor Containments."
(This
regulatory guide was withdrawn and superseded by Regulatory Guide
1.136, "Materials, Construction, and Testing of Concrete Contain-
ment.")