Only after all affected individuals and work group representatives have released
a lockout/tagout can the operations organization remove the tags (and locks, if
used) and place the equipment in an operable condition. The sequence for
removal of tags and the final position of tagged components should be specified
in the lockout/tagout procedure. As part of the restoration, the area should be
checked to ensure that:
The equipment is operationally intact, including all required guards and
interlocks.
Components within the lockout/tagout boundary are repositioned, if required,
to permit safe operations
Components that could cause automatic operation of a circuit breaker or a
motor- or air-operated valve when control power or pressure is restored are
in a position such that automatic operation will NOT occur during removal of
the lockout/tagout.
Prior to removal of a lockout/tagout, the person responsible for operation should
inform all affected personnel that the lockout/tagout is being removed and that
the equipment will be operational.
The responsible individual, supervisor or manager should account for all tags
prior to declaring the equipment operable and closing out the lockout/tagout.
One effective method is to have all tags returned to be individually verified and
destroyed or marked to prevent reuse. In some cases, such as tagouts that are
applied in contamination areas, it may not be practical to personally verify and
destroy the removed tags. Under such circumstances, alternative methods of
verification should be developed.
In facilities using individual-controlled lockout/tagout, the person who installed a
lock and tag should be the one to remove it. Each facility must develop specific
procedures to be followed for lockout/tagout removal when the individual is
unavailable, (e.g., has departed at the end of the shift). The appropriate
supervisor/manager should assume responsibility for verifying that the individual
is not available, authorizing the removal, and ensuring that the individual and all
other affected personnel are informed prior to resuming work at the facility.