| DOE-STD-1050-93
e)
Identify needed support to perform maintenance.
f)
Prepare and assemble a maintenance work package.
Activities that are not covered in this guideline, but are closely related to the planning,
scheduling, and coordinating process, include the following:
a)
procedures and work package approval
b)
work package closeout and maintenance history update
3.2.2 A sy stem of planning, scheduling, and coordinating maintenance work activities should
be clearly defined based upon the Maintenance Operations Model (Appendix A), which
consists of five interrelated processes applicable to each maintenance job. The
processes are as follows:
Plan Maintenance Job. Identify the scope of a needed maintenance job. Produce
a maintenance job plan. Determine maintenance job planning category, priority,
and safety concerns. Identify and procure materials, and identify other
maintenance task resources. Prepare the maintenance job package.
Schedule Maintenance Job. Calculate estimated start date and project resources
for the maintenance job. Schedule and commit required resources and special
tools/equipment items to allow performance of all maintenance tasks within the
maintenance job.
Execute Maintenance Job. Initiate and perform a maintenance job and collect job
information as defined in the maintenance job package.
Execute Postmaintenance Test. Verify facilities and equipment items fulfill their
design functions when returned to service after execution of a maintenance job.
Complete Maintenance Job. Perform maintenance job closeout to include
completion of all documentation contained in the maintenance job package to
ensure historical information is captured.