DOE-STD-1052-93
The following formula may be used to determine system ranking for a single
or two-unit plant:
NOTE:
LCO hours for multi-unit sites may be considered as shown
in the formula.
System score =
1.0 * [UDOL]
+ 0.04 * [LCO (Ul) + LCO (U2)]
+ 0.1 * [Survey results]
Where: U1 = Unit 1; U2 = Unit 2; * = multiply
NOTE:
The formula may be modified for a specific PM program
enhancement objective by changing or adding additional
factors along with appropriate weighting coefficients. For
example, a plant with a well-established PM program and a
strong performance record may have an objective to optimize
resources by selecting systems with a large number of PM tasks
for possible reduction while not affecting safe and reliable
operation of the system. To consider the impact of the existing
PM effort, a factor may be added to the formula that
represents the number of existing PM tasks per system or cost
to perform the tasks. Tle weighting coefficient selected should
be representative of the importance placed by management on
that factor of the formula.
7.1.3
The system selection and prioritization process should be used for the plant
systems deemed most important for nuclear safety, reliability, or economics.
Plant management should review and approve the systems selected and their
ranking. If two or more systems have equal ranking, plant management should
decide the final ranking that establishes the sequence in which the systems
should be evaluated.
It may be advisable to begin the enhancement effort by conducting a pilot
study of one system. If a pilot study is to be conducted, it may be best to start
with a system that has an unacceptable failure rate. Another criteria that may
be used for the pilot study is that a relatively simple system containing
mechanical, electrical, and electronic components be selected so all major
technical disciplines may gain experience from the study. The primary
objective of the pilot study is to refine techniques and establish guidelines for
analysis of future systems. It should be recognized that the number of systems
selected for detailed evaluation determines overall scope of the PM program
enhancement effort and the resources needed.
D - 19