| DOE-STD-1082-94
5.1.1.2 Points-of-Contact. Each Operations Office Manager shall identify
a point-of-contact for each DOE requirements document to the RISG. The
Operations Office point-of-contact shall be the primary interface with the
implementing organization for all activities associated with the development,
submittal, review, and approval of the implementation plans. The Operations
Office point-of-contact shall also be the Review Team Leader. Any exception to
the point-of-contact as the Review Team Leader shall be approved by the
Working Group. The Review Team Leader shall coordinate assignment of
Review Team members with the CSOs and the Operations Office through the
Working Group. The Operations Office Manager may also designate an office
coordinator for nuclear safety requirements activities.
5.1.1.3 Implementation Plan Review Teams. As discussed in the
previous paragraph, the Operations Office point-of-contact shall normally be the
Review Team Leader. The Operations Office Manager may provide additional
team members and technical assistance as necessary and agreed by the
Working Group. In addition, each affected CSO shall identify the Program Office
representatives for each Review Team to the Review Team Leaders through the
Working Group. The CSO may assign multiple reviewers to a single site or a
single reviewer.
5.1.2 Review Planning.
5.1.2.1 Implementation Plan Guide. For each requirements document or
group of DOE requirements documents, the Working Group shall prepare an
Implementation Plan Guide which defines DOE's specific technical and
programmatic expectations for the implementation plans. The guide shall
include the following types of information: (1) criteria and/or checklists of
items to be considered during the review, (2) approaches to key issues,
(3) direction on use of existing plans and approvals, (4) review and approval
authorities, and (5) specific issues relating to Headquarters or Operations
Office review responsibilities. The guide shall be as brief as possible,
shall be user friendly, and shall not repeat general guidance available in other
guidance documents such as this technical standard. The Working Group