| DOE-STD-1082-94
3. PREPARATION OF IMPLEMENTATION PLANS
The implementation plans detail how the site, facility, or activity has met or will
meet the nuclear safety requirements.
The format for the implementation plan is not specified. This flexibility will
permit the implementing organizations to take advantage of pre-existing
documents. For example, when making the transition from nuclear safety
Orders to nuclear safety Rules, the Department expects the implementing
organizations to use the implementation plans developed and approved for the
Orders as a basis for the Rule implementation plans. Typically, these plans
should be revised or supplemented only as necessary to reflect any new
requirements in the Rules or additional information requested in this standard or
other DOE implementation guidance. The level of detail provided in
implementation plans should be the same for Rules or Orders.
The following sections describe the minimum content expected in
implementation plans. The headings in these sections may also be used to
define the format for the plans.
3.1 Implementation Plan Summary. Each implementation plan shall
contain a summary section in the front to allow DOE management and
reviewers to quickly assess the more significant information contained in the
plan. The summary shall identify the following minimum information:
(1)
any requests for exemptions contained in the plan;
(2)
the total additional funding required to meet the requirements of
the plan and the expected sources of funding by fiscal year;
(3)
any significant new programs or activities needed to meet the
requirements;
(4)
any significant impacts to other programs or activities not included
in the plan;
(5)
any constraints to implementing the plan;
(6)
those areas where there is currently full compliance with the
requirements.
2
|
Privacy Statement - Press Release - Copyright Information. - Contact Us |