| DOE-STD-1082-94
(2)
the resources identified in the plan are necessary and
sufficient to ensure completion of the activities contained in
the plan and are expected to be available to support the
proposed schedules;
(3)
the proposed milestones and schedules are acceptable;
(4)
the applicability of the requirements is correctly identified; and
(5)
the identified compensatory actions are acceptable.
5.5 Resolution of Issues. Review and approval issues related to a
specific DOE requirements document shall be brought to the Working Group for
resolution. Issues relating to the implementation plan process as a whole, shall
be brought to the RISG for resolution.
6. REVISIONS TO IMPLEMENTATION PLANS
The implementation plans are living documents which will need to be revised
and updated during the life cycle of the site, facility, or activity.
Approved implementation plans shall be revised as needed to reflect
the addition or deletion of other work at a facility or other factors that affect the
ability to meet the approved schedule, such as prospective changes in the
level of funding or assumptions regarding the availability of materials and other
resources. Several DOE nuclear safety requirements documents contain
conditions under which implementation plans may be revised without prior
approval from DOE. In such cases the implementing organization shall submit
the revised implementation plan to DOE within 30 days of the effective date of
the plan (unless another schedule is specified in the DOE requirements
document). All other changes to implementation plans shall be reviewed and
approved by DOE prior to the effective date of the change (this does not apply
to editorial changes which do not materially change the plan or revisions
required to reflect organizational changes). Revised implementation plans
shall be submitted in a timely manner for DOE approval (generally at least 180
days before the change is to be effective), along with justification for the
revision. Proposed revisions will be considered to be approved 180 days after
submittal to DOE, unless they are approved or rejected by DOE on an earlier
date or other provisions are stated in the DOE requirements document.